Friday 7 December 2007

All a-buzz

Bricks cleaned.

Tiling beginning (thats the ensuite)

Doors fitted

Jambs, architraves etc continuing.


To-do Update
Garage door
Little bit of roof remaining
Gable 'ends'
Underneath bit of eaves
Architraves & skirting
Doors - mostly installed now
Paint
Kitchen
Tiles - have begun.
Carpet $
Plumbing fittings $
Kitchen and Vanities
Pergola/Covered area
Driveway & paths
Porch columns
Tank install - mostly done
Power connection $
Phone connection $
council Section 94 - looks like we may not have to pay this. Waiting for written confirmation from council.
Light fittings $